Louisville, Kentucky
Camp Ground Road campus (PowerHouse / Poe)
Kentucky's first hyperscale data center, in southwest Louisville. A state report says the first 130 megawatts were targeted for late 2026.
| Place | Louisville, Jefferson County, Kentucky |
|---|---|
| Developer | PowerHouse Data Centers and Poe Companies |
| Size | 335 megawatts at first, with expansion to 402 megawatts |
| Status | Being built Under construction. First phase was targeted for late 2026. Latest source dated July 25, 2026. |
| Last checked | November 9, 2026 |
What the record says
| Power | LG&E secured 335 megawatts at first, with a near-term expansion to 402 megawatts1 |
|---|---|
| First phase | 130 megawatts, targeted for commercial operation in late 2026, with a new LG&E switch station1 |
| Projected investment | About $11 billion over the life of the project1 |
| Construction | Reported as under construction in July 20262 |
Timeline
- A state commission report described the project and its power supply.1
- U.S. Rep. Morgan McGarvey wrote to LG&E opposing the project and asking who pays for the new equipment.3
What we do not know
We did not find a public record that confirms these. They are the next things to check.
- Whether the first phase is taking power (ask LG&E or check Public Service Commission filings).
- LG&E's answers to the questions in the July 2026 letter.
- Local air agency permits for backup generators.
What to do with this
The 7 first steps · Questions to ask · Comment letter builder
Other tracked projects in Kentucky
- Carrollton data center campus (Poe Companies) · Proposed
- Steele Road data center (TenKey LandCo) · Approved, in court
- Maysville hyperscale campus (Meta) · Approved, in court
- Project Bluegrass (Panattoni) · Proposed
- DECA Companies project near Ghent · Proposed
See an error or a newer record? Send us the public link.
Sources for this page
- Kentucky Energy Planning and Inventory Commission (EPIC). Report No. 2026-001, Data Centers in Kentucky: Policy Analysis for the General Assembly. June 2026. Opened November 9, 2026.
- WAVE, Louisville. Carroll County residents push back against data center project in Ghent community. July 25, 2026. Opened November 9, 2026.
- Office of U.S. Rep. Morgan McGarvey. Rep. McGarvey Opposes Camp Ground Road Data Center in Letter to LG&E. July 9, 2026. A statement by an elected official who opposes the project. Opened November 9, 2026.