Louisville, Kentucky

Camp Ground Road campus (PowerHouse / Poe)

Kentucky's first hyperscale data center, in southwest Louisville. A state report says the first 130 megawatts were targeted for late 2026.

PlaceLouisville, Jefferson County, Kentucky
DeveloperPowerHouse Data Centers and Poe Companies
Size335 megawatts at first, with expansion to 402 megawatts
StatusBeing built Under construction. First phase was targeted for late 2026.
Latest source dated July 25, 2026.
Last checkedNovember 9, 2026

What the record says

PowerLG&E secured 335 megawatts at first, with a near-term expansion to 402 megawatts1
First phase130 megawatts, targeted for commercial operation in late 2026, with a new LG&E switch station1
Projected investmentAbout $11 billion over the life of the project1
ConstructionReported as under construction in July 20262

Timeline

  1. A state commission report described the project and its power supply.1
  2. U.S. Rep. Morgan McGarvey wrote to LG&E opposing the project and asking who pays for the new equipment.3

What we do not know

We did not find a public record that confirms these. They are the next things to check.

  • Whether the first phase is taking power (ask LG&E or check Public Service Commission filings).
  • LG&E's answers to the questions in the July 2026 letter.
  • Local air agency permits for backup generators.

What to do with this

The 7 first steps · Questions to ask · Comment letter builder

Other tracked projects in Kentucky

See an error or a newer record? Send us the public link.

Sources for this page

  1. Kentucky Energy Planning and Inventory Commission (EPIC). Report No. 2026-001, Data Centers in Kentucky: Policy Analysis for the General Assembly. June 2026. Opened November 9, 2026.
  2. WAVE, Louisville. Carroll County residents push back against data center project in Ghent community. July 25, 2026. Opened November 9, 2026.
  3. Office of U.S. Rep. Morgan McGarvey. Rep. McGarvey Opposes Camp Ground Road Data Center in Letter to LG&E. July 9, 2026. A statement by an elected official who opposes the project. Opened November 9, 2026.