Free public guide. Not a government site. Not legal advice.

datacenterneighbor.comFree guide for people who live near one

Near Burgin, Kentucky

Project Bluegrass (Panattoni)

A developer wants a hyperscale data center on farmland the city of Burgin may annex. The county passed a one-year moratorium that does not cover land inside the city.

PlaceNear Burgin, Mercer County, Kentucky
DeveloperPanattoni
SizeHundreds of acres of farmland; no final plan is public
StatusProposed Proposed. The city had not annexed the land as of October 7, 2026.
Latest source dated October 7, 2026.
Last checkedNovember 9, 2026

What the record says

SiteFarmland about three miles west of Burgin1
County moratoriumOne year, on applications for new data centers in unincorporated Mercer County. The vote was unanimous on August 11, 20262
The gapThe moratorium does not apply inside Burgin. Burgin had no planning or zoning body of its own2
Developer statement"We continue to advance Project Bluegrass and work through the necessary local processes."1

Timeline

  1. The fiscal court approved a first motion for a moratorium.3
  2. The fiscal court passed the moratorium. Burgin's council had given first reading to an annexation ordinance in July.2
  3. Annexation had not happened. Burgin's council passed first reading of an ordinance to join the county planning and zoning body. The county planning body rejected a September proposal to allow data centers near the E.W. Brown power plant.1

What we do not know

We did not find a public record that confirms these. They are the next things to check.

  • Burgin City Council agendas for a second reading on annexation or on joining planning and zoning.
  • Any application filed with Mercer County planning and zoning after the moratorium ends.
  • Any Kentucky Public Service Commission filing by the utility that would serve this load.

What to do with this

The 7 first steps · Questions to ask · Comment letter builder

Other tracked projects in Kentucky

See an error or a newer record? Send us the public link.

Sources for this page

  1. Spectrum News 1 Kentucky. Burgin weighs planning and zoning move amid data center controversy. October 7, 2026. Opened November 9, 2026.
  2. WKMS / Kentucky Public Radio. A Kentucky county passes a data center moratorium — with a city-sized hole. August 12, 2026. Opened November 9, 2026.
  3. WKYT, Lexington. Mercer County Fiscal Court approves motion for data center moratorium. July 29, 2026. Opened November 9, 2026.