Speak up

How to comment at a hearing

The short answer

Send a written comment before the deadline. Then speak at the hearing and say the same thing in two minutes. Ask questions that must be answered. Speak to the issue that board decides.

Before the hearing

  1. Find the right board. Land use goes to the planning commission and the city or county board. Rates go to the utility commission. Air and water go to the state environmental agency. Use the who-decides chart.
  2. Ask the clerk the rules. How do I sign up? How long may I speak? When are written comments due? Can I send slides or photos?
  3. Read the staff report. It usually comes out a few days before the hearing. It tells you what staff recommends and why.
  4. Send your letter. Use the comment letter builder. Ask that it be entered into the record.

At the hearing

  • Say your name and address. Say how far you live from the site.
  • Say whether you support, oppose or are undecided. Any of the three is fine.
  • Ask your two or three questions. Read them if you want. Short is good.
  • Ask for a condition, not only a yes or no. "Require a sound limit at the property line" is a thing a board can do.
  • Stay polite. The record is read later by judges, reporters and other boards.

Why written comments matter

In Kentucky, a planning commission must issue findings of fact with a summary of the evidence from supporters and opponents.1 What you put in writing is part of that evidence.

State permit comments can change the permit. North Carolina issued air permits for an Amazon site in August 2026, and added emissions testing and monitoring "in response to public feedback."2 EPA explains how to comment on air permits for new sources and operating permits.

After the vote

  • Ask the clerk for the final ordinance and the list of conditions.
  • Ask what the appeal deadline is. It can be short. Talk to a lawyer fast if you plan to appeal.
  • Keep watching for the later permits: air, water, power lines.

Who else to contact

Sources for this page

  1. Kentucky Revised Statutes. KRS 100.211, Procedure for amending zoning map and text of regulation. Current text. Opened November 9, 2026.
  2. North Carolina Department of Environmental Quality. NCDEQ's Division of Air Quality requires additional monitoring, testing in final air quality permits for Amazon data center and Duke Energy projects. August 28, 2026. Opened November 9, 2026.
A full room of seated residents listening at a public hearing
Residents at a federal public hearing in Morehead City, North Carolina, in 2013. It was not about a data center. Most hearings look like this. Photo: U.S. Fish and Wildlife Service Southeast Region, Public domain.