How residents have fought data center plans, and what happened
The short answer
Residents have stopped, delayed or changed data center projects by doing four things: showing up early, asking for records, making specific points on the record, and challenging a flawed process in court. None of these is sure to work. Here are ten dated cases, including ones where the project went ahead.
This site does not tell you to oppose or support a project. People search for how to fight one, so this page shows what the public record says happened when others tried. If you support a project, the same tools apply.
Residents at a federal public hearing in Morehead City, North Carolina, in 2013. It was not about a data center. Most hearings look like this. Photo: U.S. Fish and Wildlife Service Southeast Region, Public domain.
Ten cases
August 6, 2025 · Council ended talks
Tucson, Arizona
The city council voted unanimously to end negotiations on Project Blue and pull the annexation from its agenda. The developer had wanted annexation to reach city water. The article notes the project could still be built outside city limits.1
What residents did: Weeks of public meetings. A single, clear ask: do not annex.
July 1 to 3, 2025 · Moratorium, then withdrawal
Oldham County, Kentucky
The fiscal court voted 4 to 2 for a 150-day pause on data center applications, and struck language that would have exempted the pending project.2 Within days the developer withdrew its application. It had first proposed a $6 billion project on 267 acres of farmland.3
What residents did: Packed meetings. Pressure on the exemption clause, not only on the project.
August 2025 to July 2026 · Rezoning voided in court
Prince William County, Virginia
A judge voided the rezoning for the 2,100-acre Digital Gateway campus in August 2025. The Virginia Court of Appeals upheld that on March 31, 2026.4 The last developer dropped its appeal on July 2, 2026. The county had spent nearly $2 million defending the rezoning.5
What residents did: A lawsuit about how the approval was done, brought by residents and preservation groups.
July 2026 · Rezoning denied 4 to 1
Douglas County, Georgia
Commissioners denied a rezoning for a 4.4 million-square-foot project on more than 700 acres. Neighbors brought visual props and audio clips to the hearing.6
What residents did: Showing the board what it would look and sound like.
August 2026 · Developer withdrew
Lovejoy, Georgia
A 3.5 million-square-foot, 15-building proposal between two schools was withdrawn. The developer switched to a housing plan. The city said it would start updating its zoning to prohibit data centers.7
What residents did: A specific local fact: school traffic on one road.
September 14, 2026 · Development agreement rejected
Frederick County, Maryland
The county executive rejected the site manager's application for a development agreement at the Frederick Digital Campus, and extended a pause on new data center applications to July 1, 2027. Projects already under construction continue.8
What residents did: Public comment on a draft agreement the county posted online.
August 11, 2026 · Moratorium with a gap
Mercer County, Kentucky
The fiscal court passed a one-year moratorium unanimously. It covers unincorporated land. It does not cover land the city of Burgin might annex, where the developer wants to build.9 As of October 7, 2026 the annexation had not happened.10
What residents did: Steady attendance since February. The fight moved to the city council.
June 23, 2026 · Draft rules voted down
DeKalb County, Georgia
Commissioners unanimously rejected a proposed data center zoning amendment. Residents had argued the draft was too weak and would enable projects. Others quoted in the story said the vote leaves the county in a vulnerable position.11
What residents did: Residents read the draft closely and argued over its terms.
August 28, 2026 · Permits issued, with added conditions
Richmond County, North Carolina
After a public hearing, the state issued air permits for 588 backup engines at an Amazon campus. It added emissions testing and monitoring in response to public feedback.12
What residents did: Comments did not stop the permit. They changed what it requires.
April to October 2026 · Approved; lawsuits pending
Maysville, Kentucky
Local boards approved a 2,000-acre campus. The agreement includes yearly payments to local government and schools. A citizens group has two lawsuits pending. The group says the county refused its request for low-frequency noise rules.1314
What residents did: Opposition did not stop approval. It is now in court.
What the cases have in common
Early beats late. Oldham County residents acted before a vote. In Maysville the main approvals came before the company was even named.14
Specific beats general. School traffic on one road. Water from one utility. An exemption clause in one ordinance.
Process matters. The largest project on this list was undone in court over how the approval was done.5
A pause is not a stop. A moratorium buys time to write rules. It can have gaps.9
Conditions are a result too. Monitoring, payments, berms and setbacks came from public pressure even where the project was approved.