Data Center Neighbor

Oklahoma project record

Meta Tulsa Data Center

Meta broke ground on its first Oklahoma data center in April 2026.

← Back to the national tracker · Show this project on the map

Location
Tulsa, Oklahoma
County
Tulsa County
Map point
Tulsa areaApproximate locality; not a parcel boundary.
Stage
Under construction
Evidence checked
Operator
Meta
Developer
Meta

Current snapshot

Meta’s announcement documents the groundbreaking, planned water system, grid commitments, infrastructure funding, and community programs. Those commitments remain company claims until their supporting utility, permit, and local agreements are traced.[1]

Documented scale

Announced investment
More than $1 billion[1]
Local infrastructure commitment
More than $25 million[1]

What to watch next

What this record means

This page is a dated evidence snapshot. It does not mean every approval is complete, and it does not predict whether the project will be built as announced. Follow the sources below, then confirm current deadlines with the local government, state permitting agency, and utility regulator.

Have a project that is not listed? Use the national tracking workflow to find the public record.

Sources for this page

  1. Meta

    Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma

    April 21, 2026. Accessed August 9, 2026.

    https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/

    Meta is the project owner. Investment, employment, water, energy, and community-benefit statements are the company’s own claims.

    Primary company announcement confirming the Tulsa groundbreaking and announced project scale.