Tulsa, Oklahoma
Meta Tulsa data center
Meta's first data center in Oklahoma. Figures are the company's own.
| Place | Tulsa, Tulsa County, Oklahoma |
|---|---|
| Developer | Meta |
| Size | $1 billion+ announced investment |
| Status | Being built Under construction. Ground was broken in April 2026. Latest source dated April 21, 2026. |
| Last checked | November 9, 2026 |
What the record says
| Announced investment | More than $1 billion (company figure)1 |
|---|---|
| Jobs after completion | About 100 (company figure)1 |
| Local infrastructure | More than $25 million for roads and water (company figure)1 |
Timeline
- Meta announced the groundbreaking.1
What we do not know
We did not find a public record that confirms these. They are the next things to check.
- Oklahoma Corporation Commission cases on power for the site.
- City of Tulsa water service agreements.
- Local incentive terms.
What to do with this
The 7 first steps · Questions to ask · Comment letter builder
Other tracked projects in Oklahoma
- Google Muskogee County location · In development
- Google Pryor, Mayes County location · Listed site
- Google Stillwater location · In development
- Google Tulsa location · In development
See an error or a newer record? Send us the public link.
Sources for this page
- Meta. Breaking Ground on a New AI-Optimized Data Center in Tulsa, Oklahoma. April 21, 2026. Opened November 9, 2026.