Hamlet, North Carolina
Amazon Energy Way Tech Campus
The state issued two air permits after a public hearing. It added testing and monitoring rules in response to public comment.
| Place | Hamlet, Richmond County, North Carolina |
|---|---|
| Developer | Amazon Data Services |
| Size | $10 billion announced; 588 backup engines permitted |
| Status | Permits State air permits were issued August 28, 2026. Latest source dated August 28, 2026. |
| Last checked | November 9, 2026 |
What the record says
| Announced investment | $10 billion and at least 500 jobs1 |
|---|---|
| Backup engines | 588 emergency engines allowed under Amazon's permit2 |
| Bridge power | 57 temporary Duke Energy engines, which must retire within a year of starting2 |
| Site | Airport Road, Hamlet2 |
Timeline
- The governor announced the project.1
- The state held a public hearing in Rockingham. Comments closed July 31.3
- The state issued both permits with added emissions testing and monitoring.2
What we do not know
We did not find a public record that confirms these. They are the next things to check.
- The final permit documents on the North Carolina DEQ site.
- Test results the permits require.
- The date Duke Energy's bridge engines start, which starts the one-year clock.
What to do with this
The 7 first steps · Questions to ask · Comment letter builder
Other tracked projects in North Carolina
- Meta Forest City data center · Listed site
- Google Lenoir location · Listed site
See an error or a newer record? Send us the public link.
Sources for this page
- North Carolina Department of Commerce. Governor Stein Announces Amazon Plans to Invest $10 Billion in North Carolina for AI Infrastructure. June 4, 2025. Opened November 9, 2026.
- North Carolina Department of Environmental Quality. NCDEQ's Division of Air Quality requires additional monitoring, testing in final air quality permits for Amazon data center and Duke Energy projects. August 28, 2026. Opened November 9, 2026.
- North Carolina Department of Environmental Quality. DEQ announces joint public hearing on Amazon data center and Duke Energy air quality permits in Richmond County. June 26, 2026. Opened November 9, 2026.